The currently installed and grid-connected capacity of wind energy in China is 105.5 GW. But the installation of new wind turbines especially in the north-eastern and north-western provinces of China still leads to considerable curtailment.

While the curtailment rate in 2014 could be reduced, the statistics of the National Energy Administration for the first half of 2015 prove that considerable challenges in accommodating fluctuating electricity feed-in from wind energy still exist. In the first half of 2015 the average curtailment rate across China was 15.2 %. This implies that 17.5 TWh of electricity from wind was discarded and not fed-into the grid during the first six months of 2015.

A breakdown of the numbers for the most affected provinces is shown below (NEA CN 1, NEA CN 2). The curtailment rates are depicted in percentages on the left side, the amount of the curtailed electricity in TWh on the right side.

Wind Curtailment in China H1 2015

Wind Curtailment in China H1 2015

One measure to reduce curtailment rates was proposed by the National Energy Administration earlier this year. Provinces with an average curtailment rate of more than 20% shall not plan new wind energy projects (NEA CN 3).

The article also appeared on the Chinese European Energy News portal of Energy Brainpool.

One response to “Wind curtailment in China

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s